| # CHORUS / WHOOSH Roadmap
 | ||
| 
 | ||
| _Last updated: 2025-02-15_
 | ||
| 
 | ||
| This roadmap translates the development plan into phased milestones with suggested sequencing and exit criteria. Durations are approximate and assume parallel work streams where practical.
 | ||
| 
 | ||
| ## Phase 0 – Kick-off & Scoping (Week 0)
 | ||
| - Confirm owners and staffing for SLURP, SHHH, COOEE, WHOOSH, UCXL, and KACHING work streams.
 | ||
| - Finalize engineering briefs for each deliverable; align with plan in `CHORUS-WHOOSH-development-plan.md`.
 | ||
| - Stand up tracking board (Kanban/Sprint) with milestone tags introduced below.
 | ||
| 
 | ||
| **Exit Criteria**
 | ||
| - Owners assigned and briefs approved.
 | ||
| - Roadmap milestones added to tracking tooling.
 | ||
| 
 | ||
| ## Phase 1 – Security Substrate Foundations (Weeks 1–4)
 | ||
| - **1.1 SLURP Core (Weeks 1–3)**
 | ||
|   - Implement storage/resolver/temporal components and leader integration (ticket group `SEC-SLURP`).
 | ||
|   - Ship integration tests covering admin-only operations and failover.
 | ||
| - **1.2 SHHH Sentinel (Weeks 2–4)**
 | ||
|   - Build `pkg/shhh`, integrate with COOEE/WHOOSH logging, add audit metrics (`SEC-SHHH`).
 | ||
| - **1.3 COOEE Mesh Monitoring (Weeks 3–4)**
 | ||
|   - Validate enrolment payloads, instrument mesh health, document ops runbook (`SEC-COOEE`).
 | ||
| 
 | ||
| **Exit Criteria**
 | ||
| - SLURP passes integration suite with real context resolution.
 | ||
| - SHHH redaction events visible in metrics/logs; regression tests in place.
 | ||
| - COOEE dashboards/reporting operational; runbook published.
 | ||
| 
 | ||
| ## Phase 2 – WHOOSH Data Path & Telemetry (Weeks 4–8)
 | ||
| - **2.1 Persistence & API Hardening (Weeks 4–6)**
 | ||
|   - Replace mock handlers with Postgres-backed endpoints (`WHOOSH-API`).
 | ||
| - **2.2 Analysis Ingestion (Weeks 5–7)**
 | ||
|   - Pipeline real Gitea/n8n analysis into composer/monitor (`WHOOSH-ANALYSIS`).
 | ||
| - **2.3 Deployment Telemetry (Weeks 6–8)**
 | ||
|   - Persist deployment results, emit telemetry, surface status in UI (`WHOOSH-OBS`).
 | ||
| - **2.4 Composer Enhancements (Weeks 7–8)**
 | ||
|   - Add LLM skill analysis with fallback heuristics; evaluation harness (`WHOOSH-COMP`).
 | ||
| 
 | ||
| **Exit Criteria**
 | ||
| - WHOOSH API/UI reflects live database state.
 | ||
| - Analysis-derived data present in team formation/deployment flows.
 | ||
| - Telemetry events available for KACHING integration.
 | ||
| 
 | ||
| ## Phase 3 – Cross-Cutting Governance & Tooling (Weeks 8–12)
 | ||
| - **3.1 UCXL Spec & Validator (Weeks 8–10)**
 | ||
|   - Publish Spec 1.0, ship validator CLI with CI coverage (`UCXL-SPEC`).
 | ||
| - **3.2 KACHING Telemetry (Weeks 9–11)**
 | ||
|   - Instrument CHORUS runtime & WHOOSH orchestrator, deploy ingestion/aggregation jobs (`KACHING-TELEM`).
 | ||
| - **3.3 Governance Tooling (Weeks 10–12)**
 | ||
|   - Deliver DR templates, signed assertions workflow, scope-aware RUSTLE views (`GOV-TOOLS`).
 | ||
| 
 | ||
| **Exit Criteria**
 | ||
| - UCXL validator integrated into CI for CHORUS/WHOOSH/RUSTLE.
 | ||
| - KACHING receives events and triggers quota/budget alerts.
 | ||
| - Governance docs/tooling published; RUSTLE displays redacted context correctly.
 | ||
| 
 | ||
| ## Phase 4 – Stabilization & Launch Readiness (Weeks 12–14)
 | ||
| - Regression testing across CHORUS/WHOOSH/UCXL/KACHING.
 | ||
| - Security & compliance review for SHHH and telemetry pipelines.
 | ||
| - Rollout plan: staged deployment, rollback procedures, support playbooks.
 | ||
| 
 | ||
| **Exit Criteria**
 | ||
| - All milestone tickets closed with QA sign-off.
 | ||
| - Production readiness review approved; launch window scheduled.
 | ||
| 
 | ||
| ## Tracking & Reporting
 | ||
| - Weekly status sync covering milestone burndown, risks, and cross-team blockers.
 | ||
| - Metrics dashboard to include: SLURP leader uptime, SHHH redaction counts, COOEE peer health, WHOOSH deployment success rate, UCXL validation pass rate, KACHING alert volume.
 | ||
| - Maintain Decision Records for key architecture/security choices at relevant UCXL addresses.
 |